address of the head of the community Serhiy Morgunov to the participants of REBUILD UKRAINE 2024

PROJECTS TO BE PRESENTED
AT REBUILD UKRAINE 2024

    THE PROJECT HAS AN INVESTMENT ATTRACTIVENESS

Reconstruction of a water treatment plant and reconstruction of water pumping stations

Comprehensive reconstruction of the water treatment plant and reconstruction of water pumping stations in Vinnytsia, which will involve the use of modern drinking water treatment technologies and alternative energy sources.
There are two sets of treatment facilities on the territory of the Pyatnychany water supply station. The complex of facilities at station No. 2, with a capacity of 100 thousand m3/day, was put into operation in 1969 and 1979. Plant No. 3, with a capacity of 107,000 m3/day, was commissioned in 1990. The total design capacity of the water supply system treatment facilities is 207 thousand m3/day.

The buildings are worn out, and the equipment has exceeded its useful life.

Social significance of the project:
● 400,000 residents of the Vinnytsia City Territorial Community will be provided with quality drinking water that meets modern requirements● 3.7 million m3/year - reduction of pollution of the Pivdennyi Buh river

Estimated value: 37 млн €

    Design and estimate documentation of the project: Need help
    Nature of the reconstruction: Full (rebuilding from scratch)
    Type of project ownership: Municipal
  • Water supply and drainage

    THE PROJECT HAS AN INVESTMENT ATTRACTIVENESS

Reconstruction of a sewage pumping station

Comprehensive reconstruction of the sewage pumping station on Knyaziv Koriatovychiv Street in Vinnytsia, which will include the modernisation of mechanical wastewater treatment, installation of energy-efficient equipment and introduction of alternative energy sources.The corresponding SPS pumps wastewater from the entire central part of the city to the WTP. Currently, the equipment, valves and pipelines are physically worn out. The SPS needs a complete reconstruction with an increase in capacity.
Social significance:● 30 thousand residents - living in residential buildings, working at enterprises, visiting social facilities in the central part of Vinnytsia - are covered by centralised sewerage services
● 15 thousand m3/day - uninterrupted and trouble-free pumping of wastewater by the sewage plant to the sewage treatment plant
● Improving the reliability of energy supply through the use of renewable energy sources, which will save money and reduce the load on the city's energy system.

Estimated value: 1,5 млн €

    Design and estimate documentation of the project: Need help
    Nature of the reconstruction: Full (rebuilding from scratch)
    Type of project ownership: Municipal
  • Water supply and drainage

    THE PROJECT HAS AN INVESTMENT ATTRACTIVENESS

Reconstruction of sewage pumping station 1A

Objective: Comprehensive reconstruction of the sewage pumping station on Yevhen Konovaltsia Street in Vinnytsia, which will include modernisation of wastewater treatment, installation of energy efficient equipment and introduction of alternative energy sources.
The sewage pumping station1A is the hub and the busiest station. It collects half of the city's wastewater from 20 sewage pumping stations and serves 5149 houses and transports it to the sewage treatment facilities. The sewage pumping station covers 1/3 of the city. The pumping station needs a complete reconstruction with a 1.5-2-fold increase in capacity.An emergency shutdown of any unit will lead to massive pollution and untreated wastewater entering the Pivdennyi Buh river.
Social significance:• 100 thousand residents - living in residential buildings, working at enterprises, visiting social institutions in the central part of Vinnytsia• 60 thousand m3/day - uninterrupted and trouble-free wastewater pumping by the sewage plant• Increased reliability of energy supply

Estimated value: 3,5 млн €

    Design and estimate documentation of the project: Need help
    Nature of the reconstruction: Full (rebuilding from scratch)
    Type of project ownership: Municipal
  • Water supply and drainage

    THE PROJECT HAS AN INVESTMENT ATTRACTIVENESS

Family medical center

The main objective of the project is to create a modern, innovative and comfortable medical facility to meet the needs of the population for quality medical and rehabilitation services.

The facility will serve the following categories of visitors:
Pregnant women and women with impaired reproductive system functions;
● Children (from 0 to 18 years old);
• Children with visual impairment;
● patients in need of medical rehabilitation.

To fulfil the goal, the following objectives must be achieved:
● Achieving energy efficiency class A;
● Bringing the building to full or partial energy autonomy, which will help to effectively use the saved funds for other needs of the institution;
● Replacement of all emergency structural elements of the building;
● Ensuring the safety of patients and staff in accordance with the requirements of the current legislation, including the construction of a radiation shelter with connection to the local autonomous centralised warning system and all related conditions.

Estimated value: 7,2 млн $

    Проєктно-кошторисна документація проєкту: Вже є
    Nature of reconstruction: Partial
    Type of project ownership: Municipal
  • Objects of social infrastructure (health care)

PRIORITIES for international cooperation

Vinnytsia develops twinning and partnerships with cities around the world. These relationships have created examples of successful cooperation over the past years that will allow the city to facilitate activities in support of the city’s priorities and ambitions. Our partnerships with cities focus on a variety of activities that have developed and evolved over time. Today, we attach great importance to ensuring that these city-to-city ties are strategically focused and help Vinnytsia achieve key strategic goals in all areas of city development.

The priorities for the development of international cooperation are to strengthen and synchronise the work of executive bodies, deputies, utilities, and public organisations in improving Vinnytsia's image on the international arena, revitalising economic activity, and attracting and effectively using international expert and financial resources:

    Image of a reliable international partner and an attractive tourist destination: maintaining and developing existing and establishing new international relations, international promotion of Vinnytsia, organising participation of city representatives in international internships, training, and exchanges, international promotion of Vinnytsia, organisation of participation of city representatives in international internships, training, and exchanges
    International economic cooperation: attracting foreign investment, facilitating the entry of local enterprises into foreign markets
    International economic cooperation: attracting foreign investment, facilitating the entry of local enterprises into foreign markets

Geographical features

Illustration
  • Total area – 25 633,4 hectares
    Vinnytsia region

    Vinnytsia City Territorial Community consists of 9 settlements: Vinnytsia city – the administrative center and 3 starosta districts:
    Desnyanskyi (Desna settlement), Stadnytskyi (Stadnytsia, Gavryshivka, Velyki Krushlyntsi, Mali Krusklyntsi villages), Vinnytsko-Khutirskyi (Vinnytski Khutory, Pysarivka, Schitky villages)

● Distance - 268 km from Kyiv city
● The total length of roads is 356 km, motorway and pedestrian bridges - 22, including 3 large ones across the Pivdennyi Buh River
● More than 50 intercity and international bus routes pass through the city, including to Poland, Moldova, Hungary, Slovakia, Romania, Germany, Italy, Turkey, Czech Republic, Latvia, and Lithuania.
● Vinnytsia railway station serves 1.3 million passengers annually and has connections to 23 regions of Ukraine● Vinnytsia International Airport

land and community resources

The main water artery of the community is the South Bug River, which has a total length of 806 km

  • Water use here is carried out mainly from surface sources (82% of the total volume of water intake), only 18% is taken from underground sources

LIST OF LAND RESOURCES, ha

Illustration
  • 303

    number of water bodies

  • 594

    HECTARES - the area of ​​water bodies

Investment attractiveness

Vinnytsia is one of the most attractive cities for investment in Ukraine in the conditions of hostilities,
which is confirmed by a number of independent studies.

Illustration

According to the results of the research conducted by the Rating Agency IBI-Rating, the following were confirmed:

    investment attractiveness rating at the level of invAA (excellent investment attractiveness)
    the credit rating at uaA+ grade, high creditworthiness, with a development outlook and keeping on the CreditWatch watch list.

Based on the results of the research conducted by the Credit Rating Agency, the rating has been affirmed:

    the investment attractiveness rating is at uaINV5 (the highest level)
    the credit rating is at uaAA- grade, very high creditworthiness, with a stable outlook.
  • 1

    Vinnytsia Industrial Park35, 7 ha


    Created in 2016 for 30 years

  • 2

    Vinnytsia cluster of refrigeration engineering

    19, 27 Hа

    Created in 2017 for 30 years

  • 3

    INDUSTRIAL PARK "Winter Sport"25 га


    Created in 2019 for 50 years

  • 4

    INDUSTRIAL PARK "WinIndustry"13 HA


    Created in 2022 for 30 years

industrial parks

One of the most effective mechanisms for attracting investment to a community is the creation of industrial parks. This mechanism allows for the creation of investment initiatives for the development of vacant industrial land plots, revitalisation and industrial use of land plots that have not been used for economic activity for more than 10 years.

Illustration

In accordance with the Programme for the Development of Small and Medium-Sized Enterprises of Vinnytsia City Territorial Community for 2024-2026, a number of business support mechanisms have been developed, namely:

Procedure for partial compensation of interest on loans to small and medium-sized enterprises at the expense of the Vinnytsia community budget.

Procedure for partial compensation to employers of the costs of compulsory state social insurance for newly created jobs at the expense of the Vinnytsia community budget.

Procedure for partial compensation of expenses for the purchase of equipment for the production of electricity from renewable energy sources for micro, small and medium-sized enterprises at the expense of the budget of the Vinnytsia City Territorial Community.

399,367 residents of the community

As of 01.08.2024

STRATEGIC DIRECTIONS OF COMMUNITY DEVELOPMENT:

  • Digitization of municipal space


  • Integrated community

    Quality and affordable municipal services for everyone

  • Municipal investments


  • Green economy and smart specialization

    Achieving climate neutrality

  • Affordable, safe and environmentally friendly environment


  • A vibrant city


COMMUNITY DEVELOPMENT PROGRAMMES

    Development Strategy of Vinnytsia City Territorial Community until 2030 - Strategies 3.0
    Concept of Integrated Development of Vinnytsia 2030
    Programmes of economic and social development of the community for 2024
    Programme of comprehensive restoration of the territory of Vinnytsia City Territorial Community for 2024-2027

Energy management:

    Action Plan for Sustainable Energy Development of Vinnytsia City Territorial Community until 2030 is being developed
    Action plan for 2023-2026 in the area of the European Energy Label
    Programme for the construction of solar power plants for self-consumption of electricity by municipal property of Vinnytsia City Council for 2023-2027

Ecology:

    Programme of state monitoring in the field of air protection in Vinnytsia agglomeration for 2021-2025
    Vinnytsia Green Deal Programme

Barrier-free:

    Programme for the Development of Barrier-Free Space in Vinnytsia City Territorial Community for 2024-2027

Architecture and urban planning:

    Draft amendments to the Master Plan of Vinnytsia city with updating based on the results of its monitoring and development of a land management project for changing the boundaries of Vinnytsia city
    Draft amendments to the Vinnytsia Zoning Plan
    General Plan and Zoning Plan of Pysarivka village, Vinnytsia district, Vinnytsia region

At the stage of completion:

    Comprehensive Spatial Development Plan and Draft Amendments to the General Plan of Vinnytsia City
    Master Plan and Zoning Plan for Stadnytsia village, Vinnytsia district

Information technologies:

    Informatisation and Digital Transformation Programme for 2024-2026 is in place in Vinnytsia

Civil society:

    Implementation Plan for the Strategy of Partnership between Civil Society Institutions and Vinnytsia City Council

NUMBER OF SOCIAL INFRASTRUCTURE FACILITIES IN THE TERRITORY OF THE COMMUNITY

education282

Culture44

Sport485

Medicine15

monument1Created with Sketch.

Administrative buildings10

implementation of strategic projects

Krystal – the Innovative and technology park – is a space for creating and implementing new business projects and introducing innovations to rebuild Ukraine

This is Ukraine's first municipal innovation and technology park, which will be aimed at strengthening existing and creating new high-tech and creative industries in Vinnytsia and the Podil region.

Partners/participants/donors:
Vinnytsia Municipal Investment Fund - municipal utility company, GIZ, UNDP, Vinnytsia City Council, Vinnytsia Instrumentation and Automation Cluster -public organization, Vinnytsia Club of Business People, PO, Council of Entrepreneurs under Vinnytsia City Mayor, Regional Council of Entrepreneurs under the Regional State Administration

Objective: Renovation of production facilities of old enterprises and their transformation into growth points for the creative economy and small business. Creating a space for maximum involvement of the public, youth, business, veterans and their families in setting up their own businesses, implementing start-ups, introducing business ideas and scaling them up. Cooperation with educational institutions to implement scientific developments and build strong cooperation with business

What has been done: general construction of internal and external works, interior decoration, thermal and mechanical works, installation of lifts, relocation of the boiler room, tiling, facade glazing

Vinnytsia Tourism Hub

Customer: Department of City Marketing and Tourism of Vinnytsia City Council, project idea «Made by Vinnytsia: creating an ecosystem of Vinnytsia products and value-added services»

Objective:
creating a space to bring together the community that makes Vinnytsia tourist and hospitable. The tourism hub envisages a full-fledged ecosystem in which destination management bodies, entrepreneurs, start-ups, the creative class, students of specialised education, tourism businesses and end consumers of tourism products interact. In September 2024, a tourist information centre on the ground floor of the building is scheduled to be launched in test mode

What has been done:
reconstruction of a non-residential building has been completed

Energy efficiency project

This is Ukraine's first municipal innovation and technology park, which will be aimed at strengthening existing and creating new high-tech and creative industries in Vinnytsia and the Podil region.
Partners/participants/donors:Customer: Department of Municipal Economy of Vinnytsia City Council, Vinnytsiamiskteploenergo – utility company of Vinnytsia City Council, with financial and technical support from SECO
Objective: Providing quality district heating and hot water services
What has been done: 1. Reconstruction of the heat supply system for the M. Shymka - Bilokonya neighbourhoods, including the reconstruction of an 18 MW gas boiler house, construction of a 5.3 MW solid fuel boiler house, 9.2 km of heating networks, 100 pcs.
2. Reconstruction of the heat supply system in the S. Zulinsky neighbourhood, reconstruction of a 13.5 MW gas boiler house, construction of a 3.3 MW solid fuel boiler house, 9.3 km of heating networks, 68 IHS units
3. Reconstruction of the centralised hot water supply system in the Vyshenka neighbourhood, installation of 141 hot water supply equipment

Reconstruction of the district heating system

Partners/participants/donors:
Customer:
Vinnytsiamiskteploenergo – utility company of Vinnytsia City Council,
With financial support from NEFCO – loan and grant agreement

Objective: providing quality district heating and hot water services

What has been done:

The project covered 11 residential buildings and a hospital.
The project in Vinnytsia included the following measures:
- Individual heat points - implementation of 11 individual heat points with regulation of heat supply according to the outside temperature for residential buildings.
- Installation of a new district heating plant for the hospital.
- Replacement of networks - about 1,500 m of distribution pipelines and reduction of heat losses.
- Decommissioning of an inefficient and undersized boiler house.

Project implementation results:
- Saving 4,730 MWh of heat per year
- Saving 500,000 m³ of gas per year
- Saving 80 MWh of electricity per year
- Reduction of CO2 emissions by 950 tonnes per year

Construction of block-modular cogeneration plants and power supply systems for heat supply facilities

Partners / exhibitors / donors:

Vinnytsia City Council, Vinnytsiamiskteploenergo – utility company of Vinnytsia City Council, USAID, International Organisation for Migration

Objective: construction of 5 units of block-modular cogeneration plants with a total electric capacity of 5.3 MW at the facilities of the heat supply Vinnytsiamiskteploenergo – utility company of Vinnytsia City Council to ensure the stability and continuous operation of the district heating system in Vinnytsia.

What has been done:
1. New construction of the power supply system for the facilities at CHP-1, Magistratska, 2-A and 600th anniversary, 13 PTVM-30 in Vinnytsia (Phase 1 and 2), 9.0 km cable line (Completed).
2. New construction of a block-modular cogeneration plant with a thermal capacity of 1.5 MW and an electric capacity of 1.5 MW at 13, 600-richchya Street in Vinnytsia (Completed).
3. New construction of a block-modular cogeneration plant with a thermal capacity of 1.5 MW and an electric capacity of 1.5 MW at 2, Magistratska Street in Vinnytsia (In progress).
4. Reconstruction of a block-modular cogeneration plant with a thermal capacity of 0.5 MW and an electric capacity of 0.6 MW at 12/2, Matrosa Kishky Street in Vinnytsia (In progress).
5. New construction of a block-modular cogeneration plant with a thermal capacity of 0.3 MW and an electric capacity of 0.2 MW at 9, Zulinskoho Street in Vinnytsia (In progress).
6. New construction of a block-modular cogeneration plant with a thermal capacity of 1.5 MW and an electric capacity of 1.5 MW at 13, 600-richchya Street (KVGM-50) in Vinnytsia (In progress).

Construction of the Vinnytsia Regional Clinical Treatment and Diagnostic Centre for Cardiovascular Pathology

Partners / exhibitors / donors:
Within the framework of the Loan Agreement between Ukraine and the International Bank for Reconstruction and Development and the Subsidiary Agreement on the implementation of the subproject «Health Care System Development Component of Vinnytsia region» between the Ministry of Health of Ukraine, Vinnytsia Regional State Administration and Vinnytsia City Council

Objective: Development of the healthcare system

What has been done: equipment (including medical equipment) and other non-current tangible assets totalling UAH 140.153,790 thousand were purchased at the expense of the Vinnytsia City Territorial Community budget in the period from 2021 to 2024.

Installation of an automated door opening system in shelters in the Vinnytsia City Territorial Community

Partners / exhibitors / donors:
TIRAS-12, LLC, technology companies, condominium associations, management companies

Objective: Creating safe conditions for residents and visitors of Vinnytsia after the air alert is declared. Ensuring the safety of the material and technical base and proper sanitary condition of the shelters

What has been done: as of 19.08.2024, the automated door opening system was installed in 608 shelters in the Community

Vocational guidance social project «Professional Horizons»

Partners / exhibitors / donors:
United - Ukrainian Business School for Children and Teenagers, Top Digital Marketing Agency, It Step - Computer Academy, VITA Information and Television Agency, SwitVideo Production™ Studio, Rodyna Cinema, Sadovsky Music and Drama Theatre, Artynov Creative Space, France - Hotel and Restaurant Complex, Happy Monkey - Family Restaurant, Family Confectionery Store, Vinnytsia Tourism Office, etc.

Objective: To help young people make a conscious choice about their future by getting to know different professions not theoretically but in practice. To expose the project participants to the specifics and features of different types of activities, give them the opportunity to try their hand at it and find new opportunities for themselves.

Participants: children from families of internally displaced persons, military personnel and fallen (deceased) Defenders of Ukraine.
Age category of participants: 13-17 years.

What has been done: the career guidance social project lasted from April to May 2024.
During the implementation of Professional Horizons, a number of seminars and workshops were organised for project participants with psychologists, career counsellors and career advisers.
Workshops were held with business coaches, business representatives, professionals and specialists from various industries. These events were full of practical exercises that help develop leadership skills, defend one's own point of view, make plans and achieve goals in life.

DIRECTIONS OF LOCAL ECONOMIC DEVELOPMENT

Illustration

Financial instruments to support business
In 2024, the effect was extended:

  • Procedure for partial compensation of interest on loans to small and medium-sized enterprises at the expense of the budget of the Vinnytsia City Territorial Community;

  • Artboard 22

    Procedure for partial compensation to employers of the costs of compulsory state social insurance for newly created jobs at the expense of the budget of the Vinnytsia City Territorial Community;

  • The Procedure for Partial Compensation of Costs for the Purchase of Equipment for the Production of Electricity from Renewable Energy Sources to Business Entities at the Expense of the Budget of the Vinnytsia City Territorial Community».

Programme for the development of small and medium-sized enterprises of Vinnytsia City Territorial Community for 2024-2026». The structure of the Programme's areas is based on the best European practices in economic policy to support small and medium-sized enterprises.

industry

In the community, industrial products are manufactured by more than 250 business entities from among the enterprises of the main circle

Food industry:

Illustration

PJSC "Vinnytsia Confectionery Factory"

Food industry:

Illustration

PJSC "Vinnytsia Oil and Fat Plant"

Food industry:

Illustration

LLC "Sweet Dream - Vinnytsia"

Food industry:

Illustration

PJSC "Vinnytsia Food Factory"

Food industry:

Illustration

"Avis" LLC

Food industry:

Illustration

PJSC "Vinnytsia Confectionery Factory"

Light industry:

Illustration

Volodarka PJSC

Chemical industry:

Illustration

Ukrainian-Spanish enterprise JV "Sperko Ukraine" LLC

Machine-building industry:

Illustration

PJSC Vinnytsia Plant "Mayak"

Machine-building industry:

Illustration

"GREEN COOL" LLC

Machine-building industry:

Illustration

"Promavtomatika Vinnytsia" LLC

IT industry and creative economy:

Illustration

Gemicle

IT industry and creative economy:

Illustration

Delphi Software

IT industry and creative economy:

Illustration

Playtika

IT industry and creative economy:

Illustration

LetyShops

Woodworking industry:

Illustration

Polish-Ukrainian enterprise "Barlinek Invest" LLC

Agrarian sector

It provides the population with high-quality and safe agricultural products, creates a favourable investment climate for attracting investments, promotes the creation of new jobs, increases the level of employment of the rural population and supports the development of rural areas.

    growing grain, industrial and oilseeds,
    vegetable growing, gardening,
    cattle breeding, pig breeding, sheep breeding,
    poultry farming,
    fish farming,
    beekeeping.
Illustration

In December 2022, the Programme for the Development of the Agricultural Sector and Food Security for 2023-2025 was approved

    contains - 10 areas of activity
    contains - 10 areas of activity
    covers 4 target audiences, namely: agricultural associations and farms; private farms; users of water bodies (ponds); beekeepers

The amount of funding from the community budget for 2023 is UAH 930.5 thousand, UAH 214.904 thousand has been financed, which is 23.1% of the funds provided.

Tourist potential

The tourist resources of the community are numerous museums and their unique collections.
The most popular for citizens and guests of the city are:

Illustration

The National Manor Museum of M.I. Pirogov

where the outstanding doctor, founder of military field surgery, Mykola Pirogov, lived and worked. The embalmed body of the scientist is kept here

Illustration

regional local history and art museum

located in the cells of the former Jesuit monastery

Illustration

literary and memorial museum of M.M. Kotsyubinsky

in the house where the famous writer M. Kotsyubynskyi was born and lived

Illustration

The list of monuments of architecture and urban planning of Vinnytsia includes 121 objects, of which 11 are of national importance

The oldest of the city's monuments is the historical and architectural complex "Walls"

Illustration

Artynov Tower

1911 water tower and kalancha on the European Square. Today, as a hundred years ago, the clock on the tower informs the townspeople of the exact time. Inside the tower is the Museum of the soldiers of Vinnytsia.

Illustration

entrance arch of the Central City Park

built in the 60s of the XX century.

Illustration

column of Magdeburg law

installed in the center of Vinnytsia in honor of the 360th anniversary of the city's acquisition of self-governing status.

Illustration

Roshen floating fountain

the largest floating Roshen fountain in Europe, which delights with its light and music shows from mid-April to mid-October.

Illustration

The Museum of Memory of the Victims of Nazism

the former field pond of the Nazis "Werewolf", now the "Museum of Memory of the Victims of Nazism", located 8 km from the city in the village of Clipper

Illustration

Central City Park

The stadium, planetarium, miniature park "Mini-Vinnytsia", attractions are located here.

Illustration

Park "Vyshenskyi"

where there is a lake, a beach, wooded areas, a rope park, sports grounds, boat and catamaran rentals.

Illustration

Podilsk Zoo

де розташовується озеро, пляж, заліснені території, мотузковий парк, спортивні майданчики, прокат човнів та катамаранів.

Illustration

Museum of Automotive, Photo, Television and Radio

де розташовується озеро, пляж, заліснені території, мотузковий парк, спортивні майданчики, прокат човнів та катамаранів.

Illustration

Vinnytsia gondola

де розташовується озеро, пляж, заліснені території, мотузковий парк, спортивні майданчики, прокат човнів та катамаранів.

Illustration

House of the Gospel

де розташовується озеро, пляж, заліснені території, мотузковий парк, спортивні майданчики, прокат човнів та катамаранів.

destruction

As a result of rocket attacks on the Vinnytsia urban territorial community, the following were damaged:

    4 objects of the Vinnytsia airport (Havryshivka village);
    16 objects of educational institutions with a total area of ​​6,200 m2;
    8 objects of health care institutions;
    4 cultural institutions of different forms of ownership
    1 physical culture and sports institution;
    1 public object (the building of the RATS);
    1 industrial enterprise with an area of ​​4371.9 m2;
    commercial objects of about 70 economic entities;
    public transport: 2 trams, 1 bus, 1 trolleybus.
Illustration

Vinnytsia community INVITES YOU TO COOPERATE FOR RESTORE AND DEVELOPMENT

Morgunov Serhii Anatoliyovych

Chairman of the city council

Phone: +380 (432) 595000
e-mail: au.vog.rmv%40adarniv
Vinnytsia, Ukraine, 21050. St. Soborna, bldg. 59